47 Installation Checklist (Clone)
Stage |
Item |
Sub item |
Ok |
Note |
Scope of delivery |
SYIL X5 |
|
|
|
4th axis |
|
|
|
|
Tool length probe |
Spare parts |
|
|
|
Wireless probe |
|
|
|
|
Manual pulse generator (handwheel) |
|
|
|
|
Toolbox |
E-Cabinet Keys |
|
|
|
Allen keys |
|
|
||
Optional tooling package |
|
|
|
|
Laser compensation data |
|
|
|
|
Delivery |
Number of crates |
|
|
|
Condition of crates |
|
|
|
|
Photos of crate removal |
|
|
|
|
Remove aluminium cover |
|
|
|
|
Inspect for damage |
|
|
|
|
Lifting off pallet |
|
|
|
|
Use of forklift |
|
|
|
|
Procedure: |
Remove retaining nuts |
|
|
|
Lubricate jacking screws |
|
|
||
Lift machine using jacking screws by 30-50 mm equally on all corners |
|
|
||
Lift machine off pallet |
|
|
||
While machine removed from stillage, remove the 3 cast iron feet |
|
|
||
Recover the studs holding the machine on the stillage and remove the thick washers |
|
|
||
|
|
Using the studs re-install the levelling feet into the jack screws and retain with the delivered nuts |
|
|
Place machine on the ground |
|
|
||
Moving and Seating |
Completed using: |
Forklift |
|
|
Pallet truck |
|
|
||
Visual inspection |
Enclosure |
Controller screen and keyboards |
|
|
E-stop button |
|
|
||
Traffic light |
|
|
||
Door mechanism |
|
|
||
Windows |
|
|
||
CE Mark and serial number photo |
|
|
||
Serial number of casting |
|
|
||
Coolant tray |
Electrical connector |
|
|
|
Pump |
|
|
||
T-Piece |
|
|
||
General condition |
|
|
||
E-cabinet |
All components secure |
|
|
|
Electrical terminals tight |
|
|
||
Ground strapping for door installed |
|
|
||
Save photo of e-cabinet internals |
|
|
||
Remove cover behind controller and inspect cable |
Check for connection of TTC |
|
|
|
Check connection of probe |
|
|
||
Check power supply |
|
|
||
Services installation |
Cables |
Supplied by customer |
|
|
Supplied by Installer |
|
|
||
Cable preparation |
Terminals crimped with 6 mm eyes |
|
|
|
Earth cable longer |
|
|
||
|
|
Armor of cable taped |
|
|
Shock/pull relief loop created in cable |
|
|
||
Cable gland tight |
|
|
||
Electrical connection |
4ph-N-E plug installed |
|
|
|
3ph-E plug installed |
|
|
||
Connected to isolator |
|
|
||
Air supply |
Quick connect 10 mm |
|
|
|
Direct to supply |
|
|
||
Coolant tank |
Remove levelling screws for easy moving |
|
|
|
Lift covers and clean excess oils |
|
|
|
|
Fill with water from tap |
|
|
|
|
Inspect for leaks |
Sight glass |
|
|
|
Weld seams |
|
|
||
Fix any leaks that may be present |
Clean internally and sand back paint |
|
|
|
Apply sealant |
|
|
||
Equipment connection |
MPG connection |
|
|
|
Coolant pump connection |
Electrical |
|
|
|
Hoses with PTFE |
|
|
||
Aftermarket probe connection |
Use a gland to secure cable |
|
|
|
Zip tie as needed behind controller |
|
|
||
Wash down hose |
|
|
|
|
Air gun hose |
|
|
|
|
1st Power up |
Recheck all cables |
|
|
|
With cabinet doors still open turn on machine |
|
|
|
|
Inspect LED’s inside cabinet |
|
|
|
|
Measure voltages |
phase L1 -L2 |
|
|
|
phase L1- L3 |
|
|
||
phase L2-L3 |
|
|
||
|
|
240V output |
|
|
24V output |
|
|
||
Start-up controller |
Ensure boot sequence completes |
|
|
|
Enclosure LED |
|
|
||
Traffic light |
|
|
||
Fans in E-cabinet |
|
|
||
Spindle fan |
|
|
||
Remove coolant pump cover and check rotation direction |
Adjust phases of power input if rotating incorrectly |
|
|
|
Lift Z axis to top most location |
|
|
|
|
Check air pressure switch |
|
|
|
|
Clean off shipping grease |
Apply E-Stop |
|
|
|
Clean way cover |
|
|
|
|
Clean front armour plate |
|
|
|
|
Clean bed |
|
|
|
|
Clean 4th axis |
|
|
|
|
Clean Tool setter |
|
|
|
|
Photo of bed condition as delivered |
|
|
|
|
Fluids |
Way lubrication top up |
|
|
|
Coolant mixing as per manufacturers indication |
Percentage |
|
|
|
Record serial number of controller |
Find serial number of controller and record it |
|
|
|
Create an “as delivered” backup of system on USB |
|
|
|
|
Download XML files if present |
|
|
|
|
Register with controller manufacturer |
|
|
|
|
Operational check |
Door latching |
|
|
|
Feed rate over ride knobs |
|
|
|
|
Spindle speed over ride knobs |
|
|
|
|
MPG on axes full travel |
X |
|
|
|
|
|
Y |
|
|
Z |
|
|
||
A |
|
|
||
B |
|
|
||
Feed rate buttons |
|
|
|
|
Rapid feed button with door close |
|
|
|
|
Rapid feed rate button with door open |
|
|
|
|
Load tool manually for drawbar operation |
|
|
|
|
Spindle on/off with door closed (tool loaded only) |
|
|
|
|
Spindle on/off with door close |
|
|
|
|
Spindle operation |
Check spindle runout at 200 or 300 mm |
|
|
|
Spindle warm-up from 1,000 RPM to max over 30 minutes |
Check temperature is not excessive |
|
|
|
Check E-stop operation of spindle at 3,000 RPM |
Dead stop |
|
|
|
Axis operation |
Feed full axis travel and record max min |
X |
|
|
Y |
|
|
||
Z |
|
|
||
Feed at full rapid and sound check |
X |
|
|
|
Y |
|
|
||
Z |
|
|
||
Run tool change test program |
|
|
|
|
Probe Calibration |
Toolsetter |
Length Calibration |
|
|
|
|
Radius Calibration |
|
|
Wireless probe |
Length Calibration |
|
|
|
|
Radius Calibrations |
|
|
|
Functional test |
Toolsetter |
|
|
|
|
Wireless probe |
|
|